Constructing the network sit preparation project
TABLE 1 SITE Preparation project
Task Title Predecessors Duration
A contract approval ------ 5
B site survey a 5
C permit application a 4
D grading b, c 5
E sewer lines b 7
F base paving d 3
G city approval c, f 6
H final Paving e, g 8
Using the above information complete the following tasks:
1. Construct this network using Microsoft project 2013
2. Identify the critical path. how long will the project take?
3. Assign and level resources
4. Suppose rose is responsible for activities b and c . are there any resource conflicts? How do we know.
5. Show the same project using a gantt chart and a network diagram.