Constructing project network for a project


Assignment:

Consider a project with the following activity list.

Activity Immediate Predecessors Estimated Duration (months)
A - 1
B A 2
C B 4
D B 3
E B 2
F C 3
G D,E 5
H F 1
I G,H 4
J I 2
K I 3
L J 3
M K 5
N L 4

a. Construct the project network for this project.

b. Find the earliest start time and earliest finish time for each activity.

c. Find the latest start time and latest finish time for each activity.

d. Find the slack for each activity. Which of the paths is a critical path?

Provide complete and step by step solution for the question and show calculations and use formulas.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Constructing project network for a project
Reference No:- TGS01999809

Expected delivery within 24 Hours