Question 1:
Illustrate the reasons why project planning is an iterative process and why a plan should be reviewed during the course of the software project, hence, construct a Gantt chart to represent Table below showing clearly the float for each task.
Question 2:
Consider the sequence of events in Table below. Construct a PERT chart, determining the following (justifying any assumptions made in computing the critical path):
i. Critical Path
ii. Earliest Completion Time - ECT
iii. Latest Completion Time - LCT
iv. Slacks
Question 3:
If task T5 were to extend to 40 days in duration, what effect would this have on the duration of project as a whole, hence, revise the critical path accordingly?
Task
|
Duration (days)
|
Dependencies
|
T1
|
10
|
|
T2
|
15
|
T1
|
T3
|
10
|
T1,T2
|
T4
|
20
|
|
T5
|
10
|
|
T6
|
15
|
T3,T4
|
T7
|
20
|
T3
|
T8
|
35
|
T7
|
T9
|
15
|
T3, T6
|
T10
|
5
|
T5, T9
|
T11
|
10
|
T9
|
T12
|
20
|
T10
|
T13
|
35
|
T3, T4
|
T14
|
10
|
T8, T9
|
T15
|
20
|
T9, T14
|
T16
|
10
|
T15
|