Constructing pert chart


Question 1:

Illustrate the reasons why project planning is an iterative process and why a plan should be reviewed during the course of the software project, hence, construct a Gantt chart to represent Table below showing clearly the float for each task.

Question 2:

Consider the sequence of events in Table below. Construct a PERT chart, determining the following (justifying any assumptions made in computing the critical path):

i. Critical Path

ii. Earliest Completion Time - ECT

iii. Latest Completion Time - LCT

iv. Slacks

Question 3:

If task T5 were to extend to 40 days in duration, what effect would this have on the duration of project as a whole, hence, revise the critical path accordingly?

Task

Duration (days)

Dependencies

T1 

10

 

T2

15

T1

T3

10

T1,T2

T4

20

 

T5

10

 

T6

15

T3,T4

T7

20

T3

T8

35

T7

T9

15

T3, T6

T10

5

T5, T9

T11

10

T9

T12

20

T10

T13

35

T3, T4

T14

10

T8, T9

T15

20

T9, T14

T16

10

T15

 