Constructing a gantt chart for the project


Question: Construct a Gantt chart for the project described by the following set of activities, and indicates the project completion time and available slack for each activities. Please see the following table:

  Activity Predecessor Time (Weeks)
  -     3
  -     7
  1     2
  2     5
  2     6
  4     1
  5     4

Solution Preview :

Prepared by a verified Expert
Project Management: Constructing a gantt chart for the project
Reference No:- TGS01953749

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)