Question: Construct a Gantt chart for the project described by the following set of activities, and indicates the project completion time and available slack for each activities. Please see the following table:
|
Activity Predecessor |
Time (Weeks) |
|
- |
|
|
3 |
|
- |
|
|
7 |
|
1 |
|
|
2 |
|
2 |
|
|
5 |
|
2 |
|
|
6 |
|
4 |
|
|
1 |
|
5 |
|
|
4 |