Construct the project network for this project find the


Question: Consider a project with the following activity list.

Activity Immediate Predecessors Estimated Duration (months)
A - 1
B A 2
C B 4
D B 3
E B 2
F C 3
G D,E 5
H F 1
I G,H 4
J I 2
K I 3
L J 3
M K 5
N L 4

a. Construct the project network for this project.

b. Find the earliest start time and earliest finish time for each activity.

c. Find the latest start time and latest finish time for each activity.

d. Find the slack for each activity. Which of the paths is a critical path?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Construct the project network for this project find the
Reference No:- TGS02654339

Expected delivery within 24 Hours