Construct the pert network diagram - state the critical


Time Management - Scheduling

Your project team presented you with the above information. You now need to:

1. Construct the PERT Network Diagram

2. State the Critical Path of the project

3. Present the ES, EF, LS, LF and Slack for activities B, D & F

4. Calculate and state the variance for the project

5. Calculate and state the standard deviation for the project

6. The sponsor for the project would like to know the probability of completing the project within 30 days. Kindly calculate and state this in percentage.

ACTIVITY

PREDECESSOR

OPTIMISTIC TIME

NORMAL TIME

PESSIMISTIC TIME

A

-

6

5

10

B

-

9.2

6

10

C

A

10.6

8

16.2

D

A

9.8

7.3

10.02

E

B, C

10.3

5.5

11.68

F

D

10

4

13

G

E

9.1

8

20.1

Solution Preview :

Prepared by a verified Expert
Project Management: Construct the pert network diagram - state the critical
Reference No:- TGS01066604

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)