Problem: Screening Model.
Assume that the following criteria relevant to the process of screening various project opportunities are weighted in importance as follows:
Quality (7)
Cost (3)
Speed to market (5)
Visibility (1)
Reliability (7)
Our company has four project alternatives that satisfy these key features as follows:
Construct a project screening matrix to identify among these four projects the most likely candidate to be implemented.