Express Delivery Company acquired an adjacent lot to construct a new warehouse, paying $80,000 and giving a short-term note for $620,000. Legal fees paid were $1,900, delinquent taxes assumed were $9,000, and fees paid to remove an old building from the land were $6,000. Materials salvaged from the demolition of the building were sold for $1,175. A contractor was paid $800,000 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet.