ZUMA Part 1
The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.
The Project Priority Matrix for the Red Zuma Project is:
|
Time |
Scope |
Cost |
Constrain |
|
X |
|
Enhance |
X |
|
|
Accept |
|
|
X |
Part 1
You are a member of a project team assigned to develop the new razor scooter code named "Red Zuma." Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following:
TABLE A Red Zuma: Project Schedule
ID
|
Task Name
|
Duration
|
Predecessors
|
1
|
1 Red Zuma Project
|
260 days
|
|
2
|
1.1 Market Analysis
|
25 days
|
|
3
|
1.2 Product Design
|
30 days
|
2
|
4
|
1.3 Manufacturing Study
|
20 days
|
2
|
5
|
1.4 Product Design Selection
|
10 days
|
3, 4
|
6
|
1.5 Detailed Marketing Plan
|
15 days
|
5
|
7
|
1.6 Manufacturing Process
|
30 days
|
5
|
8
|
1.7 Detailed Product Design
|
45 days
|
5
|
9
|
1.8 Build Prototypes
|
25 days
|
8
|
10
|
1.9 Lab Test Prototypes
|
10 days
|
9
|
11
|
1.10 Field Test Prototypes
|
15 days
|
9
|
12
|
1.11 Finalized Product Design
|
20 days
|
7,10,11
|
13
|
1.12 Final Manufacturing Process
|
10 days
|
12
|
14
|
1.13 Order Components
|
7 days
|
12
|
15
|
1.14 Order Production Equipment
|
14 days
|
13
|
16
|
1.15 Install Production Equipment
|
35 days
|
14FS+20 days, 15FS+30 days
|
17
|
1.16 Celebrate
|
1 days
|
6, 16
|
Note: FS refers to a Finish-to-Start lag.
1. The project begins January 2, 2015.
2. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.
3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.
4. The project team works eight-hour days, Monday through Friday.
Construct a network schedule for this project and prepare a memo that answers the following questions:
1. When is the project estimated to be completed? How long will the project take?
2. What is the critical path for the project?
3. Which activity has the greatest amount of slack?
4. How sensitive is this network?
5. Identify two sensible milestones and explain your choices.
Include the following printouts:
• A Gantt chart.
• A network diagram highlighting the critical path.
• A schedule table reporting ES, LS, EF, LF, and slack for each activity.