Question 1. Construct a network diagram using AON notation
Activity Activity time(weeks) Immediate Predecessor(s)
A 3 NONE
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F
Question 2. Using the network diagram constructed in question 1
a) Calculate the completion time for the project
b) Determine which activities are included on the critical path