Construct a network diagram for the project


Solve the below problem:

Q: The following data were obtained from an in-house MIS project

Activity           Duration         Predecessors 

A                     5 Days            ---                               

B                     8 Days            ---                               

C                     5 Days            A                                

D                     4 Days            B

E                      5 Days            B                                

F                      3 Day              C, D               

G                     7 Days            C, D

H                     6 Days            E, F, G

I                       9 Days            E, F

Step 1: Construct a network diagram for the project.

Step 2: response the following questions

a) Calculate the scheduled completion time.

b) Identify the critical path (6 points)

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?

Request for Solution File

Ask an Expert for Answer!!
Operating System: Construct a network diagram for the project
Reference No:- TGS01867915

Expected delivery within 24 Hours