Assignment:
Question 1. Given the information provided below and the Gantt chart layout provided, you are to construct a Gantt chart, with overlaps as specified.
Activity Letter
|
Activity Description
|
Predecessor
|
Duration (months)
|
Overlap (months)
|
A
|
Train project team
|
None
|
1
|
None
|
B
|
Project paperwork and systems design
|
A
|
2 ½
|
¼
|
C
|
Modify purchased package
|
B
|
2
|
1
|
D
|
Manual systems flow
|
B
|
1 ½
|
1
|
E
|
Modify in-house procedures
|
B
|
4
|
1
|
F
|
Test and implement modifications to purchased package
|
C
|
1 ½
|
1/8
|
G
|
Test and implement manual
|
D
|
¾
|
1/8
|
H
|
Test and implement modifications to in-house procedures
|
E
|
1
|
1/8
|
Please review the document enclosed here:
Attachment:- Gantt chart.rar