You and your team are awarded a 1 year contract to supply/deliver, construct, test and commissioning of a 20 units 2-storey shophouse near your hometown. Construct a financial plan to illustrate your preparation of material and manpower delivery plan comprehensively.
Assuming the total budget will be $20,000,000.