Consider this excerpt from the integrated program


Consider this excerpt from the Integrated Program Management Report (IPMR) Format 3. What can you tell about the contract addressed by this information?

(IMAGE DESCRIPTION: IPMR Format 3 contract data values, in thousands of dollars, are: a. original negotiated cost $64,711.5; b. negotiated contract changes $65.4; c. current negotiated cost (a+b) $64,776.9; d. estimated cost of authorized unpriced work $2,129.0; e. contract budget base (c+d) $66,905.9.)