Consider the Western Hills Shopping Center Project summarized by the below figure and table. Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but has three weeks remaining. Activities C and D have not started yet. Activity B has one week remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed?
If any activity is completed, then enter the text "NA" as your answer.
Updated activity schedule for the western hills shopping center project
|
Earliest
|
Latest
|
Earliest
|
Latest
|
|
|
|
Start
|
Start
|
Finish
|
Finish
|
Slack
|
Critical
|
Activity
|
(ES)
|
(LS)
|
(EF)
|
(LF)
|
(LS - ES)
|
Path?
|
A
|
0
|
0
|
5
|
5
|
0
|
Yes
|
B
|
|
|
|
|
|
- Select your answer -YesNoNAItem 12
|
C
|
|
|
|
|
|
- Select your answer -YesNoNAItem 18
|
D
|
|
|
|
|
|
- Select your answer -YesNoNAItem 24
|
E
|
|
|
|
|
|
- Select your answer -YesNoNAItem 30
|
F
|
|
|
|
|
|
- Select your answer -YesNoNAItem 36
|
G
|
|
|
|
|
|
- Select your answer -YesNoNAItem 42
|
H
|
|
|
|
|
|
- Select your answer -YesNoNAItem 48
|
I
|
|
|
|
|
|
- Select your answer -YesNoNAItem 54
|