Consider the Western Hills Shopping Center Project summarized by the below figure and table. Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but has three weeks remaining. Activities C and D have not started yet. Activity B has one week remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed?
![1357_Problem 13.5 Q (2).JPG](https://secure.tutorsglobe.com/CMSImages/1357_Problem%2013.5%20Q%20(2).JPG)
![1240_Problem 13.5 Q (2).JPG](https://secure.tutorsglobe.com/CMSImages/1240_Problem%2013.5%20Q%20(2).JPG)
If any activity is completed, then enter the text "NA" as your answer.
Updated activity schedule for the western hills shopping center project
|
Earliest
|
Latest
|
Earliest
|
Latest
|
|
|
|
Start
|
Start
|
Finish
|
Finish
|
Slack
|
Critical
|
Activity
|
(ES)
|
(LS)
|
(EF)
|
(LF)
|
(LS - ES)
|
Path?
|
A
|
0
|
0
|
5
|
5
|
0
|
Yes
|
B
|
|
|
|
|
|
- Select your answer -YesNoNAItem 12
|
C
|
|
|
|
|
|
- Select your answer -YesNoNAItem 18
|
D
|
|
|
|
|
|
- Select your answer -YesNoNAItem 24
|
E
|
|
|
|
|
|
- Select your answer -YesNoNAItem 30
|
F
|
|
|
|
|
|
- Select your answer -YesNoNAItem 36
|
G
|
|
|
|
|
|
- Select your answer -YesNoNAItem 42
|
H
|
|
|
|
|
|
- Select your answer -YesNoNAItem 48
|
I
|
|
|
|
|
|
- Select your answer -YesNoNAItem 54
|