Question: Consider the project network pictured in Figure. Assume that the times attached to each node are the means and the variances of the project completion times, respectively.
a. Identify all paths from nodes 1 to 6.
b. Which path is critical based on the expected completion times?
c. Determine the probability that the project is completed within 20 weeks assuming that the path identified in part (b) is critical.
d. Using independence of paths A-C-E and B-F-G only, recompute the answer to part (c).
e. Recompute the answer to part (c) assuming independence of the paths identified in part (a).
f. Which answer, (c), (d), or (e), is probably the most accurate?