Question: Consider the project described in Problem. The tasks require both welders and pipe fitters. The requirements are
a. Determine the load profiles for welders and pipe fitters assuming an early-start schedule.
b. Determine the load profiles assuming a late-start schedule
Problem: A project consists of seven activities. The precedence relationships are given in the following table.
a. Construct a network for this project.
b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.
c. Draw a Gantt chart of the schedule for this project based on earliest starting times.
d. What group of activities will have to be completed by day 60 in order to guarantee that the project will not be delayed?