Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will be completed within 205 days? Multiple Choice 0.9544 0.6826 0.9987 0.9772 0.8413