Consider the following work breakdown structure time


Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will be completed within 205 days? Multiple Choice 0.9544 0.6826 0.9987 0.9772 0.8413

Request for Solution File

Ask an Expert for Answer!!
Business Management: Consider the following work breakdown structure time
Reference No:- TGS02887608

Expected delivery within 24 Hours