Consider the following three-station production line with a single product that must visit stations 1, 2, and 3 in sequence. its total production line time is 3 hrs 47 mins, bottle neck rate is 200, Wo is 9.333.
- Can the three station production line make this takt time? If not how many machines would I need at station 1, 2, and 3? calculate takt time.
please show calculations and diagram