Consider the following project activities, their cost, baseline time, actual time spent, and estimated time to completion:
Task Estimated Cost per hour Baseline Duration Actual time spent Estimated time to finish
A $75 14 hr 15 hr 1 hr
B $92 19 hr 18 hr 2 hr
C $135 11 hr 9 hr 2 hr
D $110 13 hr 13 hr 1 hr
Calculate the following project values showing your work:
Planned Value
Actual Cost
Earned Value
Schedule Variance
Cost Variance
Schedule Performance Index and
Cost Performance Index