Consider the following project activities, their cost, baseline time, actual time spent, and estimated time to completion:
Task Estimated Cost per hour Baseline Duration Actual time spent Estimated time to finish
A $75 14 hr 15 hr 1 hr
Calculate the following project values showing your work:
- Planned Value
- Actual Cost
- Earned Value
- Schedule Variance
- Cost Variance
- Schedule Performance Index and
- Cost Performance Index