Consider the following cash flows for three mutually exclusive projects. What is the IRR of the project you should accept? Assume an interest rate of 12% Year A B C 0 −$950,000 −$1,790,000 -$1,000,000 1 370,000 800,000 660,000 2 510,000 800,000 550,000 3 420,000 750,000 340,000 What is the IRR of the project the company should adopt? this should be done in excel.