Consider the figure shown below. Assume the length of lines XY and YZ are equal and each relay covers 80% of length in its primary zone. If the fault occurs on the line XY at 50% of its length, then the correct sequence of operation of relay is
Relay A B C D
Operating time (ms) 80 120 90 100