Consider Table 6-2, Network Diagram Data for a Small Project.All duration estimates or estimates times are in days, and the network proceeds from Node 1 to Node 9.(Please answer the questions for Chapter 6, number 2 under Exercises, pp 246.)
ACTIVITY |
INITIAL NODE |
FINAL NODE |
ESTIMATED DURATION |
A |
1 |
2 |
2 |
B |
2 |
3 |
2 |
C |
2 |
4 |
3 |
D |
2 |
5 |
4 |
E |
3 |
6 |
2 |
F |
4 |
6 |
3 |
G |
5 |
7 |
6 |
H |
6 |
8 |
2 |
I |
6 |
7 |
5 |
J |
7 |
8 |
1 |
K |
8 |
9 |
2 |