Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 10, 17, 35. Find the mean value of the activity time. Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 8, 18, 32. Find the standard deviation of the activity time.