Consider a project where expected time is 43 days and


Consider a project where Expected time is 43 days and standard deviation of the project is 8 days. The project manager has agreed to deliver the project by 41 days. What is the probability the project manager would be able to complete the project in 41 days?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Consider a project where expected time is 43 days and
Reference No:- TGS0561823

Expected delivery within 24 Hours