Question - Consider a project having the following ten activities:
Activity
|
Immediate Predecessors
|
Optimistic Time (o) (weeks)
|
Most likely Time (m) (weeks)
|
Pessimistic Timer (p) (weeks)
|
A
|
none
|
1
|
5
|
9
|
B
|
A
|
6
|
6
|
6
|
C
|
A
|
3
|
5
|
9
|
D
|
A
|
2
|
4
|
6
|
E
|
B, C
|
4
|
4
|
4
|
F
|
D
|
4
|
7
|
8
|
G
|
E
|
2
|
2
|
8
|
H
|
E, F
|
7
|
8
|
9
|
I
|
F
|
4
|
6
|
9
|
J
|
G, H, I
|
3
|
5
|
7
|
Required - What is the expected project completion time.