Question - Consider a project having the following ten activities:
Optimistic Most likely Pessimistic
Immediate Time (o) Time (m) Time (p)
Activity Predecessors (weeks) (weeks) (weeks)
A none 1 5 9
B A 6 6 6
C A 3 5 9
D A 2 4 6
E B, C 4 4 4
F D 4 7 8
G E 2 2 8
H E, F 7 8 9
I F 4 6 9
J G, H, I 3 5 7
What is the expected time for each activity?