Consider a production line with four single-machine station


Consider a production line with four single-machine station in series. Each has processing times with mean 3 hours and standard deviation of 1.8 hours.

a) Suppose we run this line as a push system and release jobs into the line at a rate of 0.4 per hour with arrival variability given by Ca = 1.

What is the average WIP in the line?

b) Compute the throughput of this line if it is run as a CONWIP line with a WIP level equal to your answer in (a). Is the throughput higher or lower than 0.4? Explain this result.

Suppose the marginal profit is $70 per piece and the cost of WIP is $0.40 per piece per hour.

c) What is the profit from the push system if we set at 0.3?

d) What is the profit from the pull systems if we set at 15?