Consider a process which is divided in 3 separate stages. For this process you've collected the following information:
If we assume that the bottleneck works with a 100 % utilization, and that no costs come from waiting or transferring items between stages, what are the total costs of underutilization per hour for this process? Note that the flow rate has been given as pc/minute.
A rounding error of 0.1 is accepted in entering the answer. Note that your answer should be a decimal in the format 0.1.