Consider a capacity constrained process producing a high profit margin product. What will the impacts on revenue and profits be if processing time for the bottleneck resource is reduced by 10% while everything else remains the same?
A) No impact on revenue or profits
B) Higher revenue and profits
C) Lower revenue and profits
D) Higher profits with no change in revenue