Assignment:
Given is a PERT project network diagram as shown below.
Activity
|
Start
|
A
|
B
|
C
|
D
|
E
|
F
|
G
|
H
|
End
|
Time
|
0
|
3.35
|
1.35
|
3.15
|
1.89
|
5.14
|
3.65
|
2.18
|
1.89
|
0 |
a) The Project Completion time = _________ (in 2 decimal places)
b) The Earliest Start time, ES, of Activity G = ____________ (in 2 decimal places)
c) The Latest Finish time, LF, of Activity C =_____________ (in 2 decimal places)
d) The critical activities are =____________ (ex. type in critical activities as ABCD, no comma, no space)
Provide complete and step by step solution for the question and show calculations and use formulas.