Computing the optimal run size


Assignment:

The Friendly Sausage Factory (FSF) can produce hot dogs at a rate of 5,000 per day. FSF supplies hot dogs to local restaurants at a steady rate of 260 per day. The cost to prepare the equipment for producing hot dogs is $66. Annual holding costs are 45 cents per hot dog. The factory operates 295 days a year.

a. Find the optimal run size. (Do not round intermediate calculations. Round your answer to the nearest whole number.)
b. Find the number of runs per year. (Round your answer to the nearest whole number.)
c. Find the length (in days) of a run. (Round your answer to the nearest whole number.)

Provide complete and step by step solution for the question and show calculations and use formulas.