Computing the cycle time per day


Assignment:

Given the following manufacturing precedence relationships and assuming eight working hours a day and 310 products need to be produced per day.

Task

Description

Task Time (seconds)

Preceding Task

A

Punching

16


B

Bending

22

A

C

Combining

17

B

D

Painting

34

C

E

Polishing

35

D

  • What is the cycle time per day in the unit of second?

Provide complete and step by step solution for the question and show calculations and use formulas.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Computing the cycle time per day