1. Given the following activities and precedence's, draw ADM or PERT or PDM/CPM diagram:
Activity |
Immediate Predecessor |
A |
- |
B |
- |
C |
A |
D |
A,B |
E |
A,B |
F |
C |
G |
D,F |
H |
E,G |
2. Given the estimated times below and network
Activity |
a |
m |
b |
A |
6.5 |
7.5 |
14.5 |
B |
8.5 |
10.5 |
12.5 |
C |
2.5 |
3.5 |
4.5 |
D |
6.5 |
7.5 |
8.5 |
E |
5.5 |
5.5 |
9.5 |
F |
5.5 |
7.5 |
9.5 |
G |
4.5 |
6.5 |
8.5 |
H |
2.5 |
3.5 |
3.5 |
Find out the critical path probability that the project will be completed in:
(a) 21 days?
(b) 22 days?
(c) 25 days?