Computing probability of the network


There are three (and only three) paths through a network (project), each with a probability of completion in less than 24 months as indicated:

a. S-a-b-F P1(<24) = .95

b. S- d-e-F P2(<24) = .85

c. S- g-h-F P3(<24) = .90

If the tasks are independent, what is the probability of the network being completed within 24 months? Note: S is the start node, F is the finish node.