Assignment:

Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 40 weeks? Assume that activity A actually finished at 3 weeks, activity B actually finished at 12 weeks, and activity C finished at 13 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule?

720_Calculate the ES.JPG

Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.