Assignment:
Below durations, what activities each must precede and the crash cost to reduce duration per week:
Activity |
Duration |
Precedes |
Crash cost |
A |
2 |
B,C |
300 |
B |
2 |
E |
100 |
C |
4 |
F |
175 |
E |
1 |
F |
140 |
F |
2 |
|
400 |
Suppose that you have 5 weeks (instead of 8)to complete the project. By how many weeks should each activity be crashed in order to meet the deadline Assume that you can crash an activity down to 0 weeks duration.