Q1) Sprint Manufacturing Company evaluates that it will consume 400,000 units of Part 101 in coming year. Ordering cost for this unit is $3.20. What would be carrying costs per unit if EOQ model points out that it is optimal to place exactly 50 orders for upcoming year?