Response to the following problem:
Tri-State Mill uses a special sander to finish lumber. Data on the sander and its usage follow:Cost Driver Rate ,Cost Driver Volume
Resources used energy................................$ 0.90 per machine-hour
4,000 machine-hou repairs.................................$ 16.00 per job
400 jobs Resources supplied.. Energy.................$4,000
Repairs....................................8,000
Required
Compute unused resource capacity in energy and repairs for Tri-State Mill.
Reference: Fundamentals of Cost Accounting-Publisher: McGraw-Hill Higher Education