Compute true status of the project on tasks


Compute true status of the project on tasks a and b. Information that is given is:

Budgeted Work/Cost (PV)
Actual Cost to date (AC)
% work completed
Estimate to complete
Planned start & end dates - Start is Jan. 1, End is April 30
Actual start date - Feb. 1
Projected end date
Planned Resources Utilized - 30%
Actual Resources Utilized - 45%

With Cost one computes PV EV and AC.

The formula concerning schedule and cost refers to financial data but when there are only dates how does that calculation go?