1-Compute the material price variance (MPV).
MPV = AQ (AP-SP) or Material Price Variance = Actual Quantity (Actual Price - Standard Price)
2-Provide the entry for the price variance.
Beginning Inventory Steel
|
|
|
Material Price Variance
|
|
|
Accounts Payable
|
|
|
Labor
1-Compute the labor rate variance (LRV).
LRV= AH (AR-SR) or Labor Rate Variance = Actual Quantity of Hours (Actual Rate Per Hour - Standard Rate Per Hour)
2-Compute the labor efficiency variance (LEV).
LEV = SR (AH-SH) or Labor Efficiency Variance = Standard Labor Rate (Actual Labor Hours Used - Standard Hours)
3-Provide the accounting entry for the labor rate and efficiency variances.
Work in Process
|
|
|
Labor Efficiency Variance
|
|
|
Labor Rate Variance
|
|
|
Wages Payable
|
|
|
Overhead
1-Compute the variable overhead rate variance (VRV)
VRV = AH (AR-SR) or Variable Overhead Rate Variance = Actual Quantity Per Hour (Actual Rate - Standard Rate)
2-Compute the variable overhead efficiency variance (VOEV).
VOEV = SR (AH-SH ) or Variable Overhead Efficiency Variance = Standard Rate (Actual Hours Used - Standard Hours)
3-Provide the accounting entry for the overhead rate and efficiency variances.
Work in Process
|
|
|
Variable Overhead Efficiency Variance
|
|
|
Variable Rate Variance
|
|
|
Accounts Payable
|
|
|