Compute the value-added and non-value-added


Christmas Express makes wreaths in batch sizes of 12. The cutting & assembly process takes 7 minutes per wreath and the decorating process time is 10 minutes per wreath. It takes 12 minutes to move the wreaths from the cutting & assembly process to the decorating process.

a. Compute the value-added, non-value-added, and the total lead time of the wreath process.

Value-added lead time
Non-value-added lead time:
Move time
Within batch wait time
Total lead time

b. Compute the value-added ratio. Round to one decimal place.
%