Compute the unit costs for the month


Problem:

The Smelting Department of Polzin Company has the following production and cost data for September. Production: Beginning work in process 2,000 units that are 100% complete as to materials and 20% complete as to conversion costs; units started and finished 9,000 units; and ending work in process 1,000 units that are 100% complete as to materials and 40% complete as to conversion costs. Manufacturing costs: Work in process, September 1, $15,200; materials added $60,000; labor and overhead $132,000. Polzin uses the FIFO method to compute equivalent units.

Required:

Question: Compute the unit costs for the month.

Note: Please provide full description.