Compute the total direct cost for each project duration


Question:

Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), $25 (16) compute the total project cost for each duratin. Plot the total direct, indirect and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project and the cost?

ID    Slope    Maximum Normal Normal
Crash Time Time    Cost

a    20    1    3    50
b    60    2    5    60
c    40    1    3    70
d    0      0   10   50
e    50    3    6    100
f    100   3    7    90
g    70    1    5    50