Compute the takt time (minutes per unit) for a system given the following data:
There is a single worker per shift with a total time per shift of 480 minutes.
There is/are 1 shift(s), and workers are given two 20 minute breaks and 35 for lunch.
Daily demand is 340 units.
(Keep two decimal places in your answer).