Each employee takes two 15 minute rest breaks and one 35 lunch break each shift. The company has 3 shifts per work day each with 5 employees. Compute the takt time for a full day (all shifts) if the company is planning to produce 1000 JU-4s. Note: Keep two decimal places in your answer. The answer is in minutes per JU-4.