The following data were obtained from the project to build the pressure vessel:
Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I
Create network for project. Then review and answer (A) and (B).
(A.) Compute the scheduled completion time and recognize critical path.
(B.) Determine the slack time (float) for activities A, D, E, and G?