Compute the projected available balance


Discuss the below:

Q: The Shades Sunglass Company assembles sunglasses from frames, which it makes, and lenses, which it purchases from an outside supplier. The sales department has prepared the following 6-week forecast for Ebony, a popular model. The sunglasses are assembled in lots of 200, and the opening inventory is 300 pairs. Complete the projected available balance and the master production schedule.

Week 1 2 3 4 5 6
Forecast Sales 200 300 350 200 150 150
Projected Available Balance 300