Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q
Time: 0 1 2 3 4
Cash flow –$12,300 $4,000 $4,830 $2,170 $2,800